January 2024.
The end of the project is nearing with the delivery of 2 vehicles. The last 2 still to follow.
December 2023.
Delivery of the first 4 vehicles of the last additional order.
April 2023.
Delivery of 6 vehicles for a different division with a slightly different specification. Due to the higher curb-weight, a whole set of homologation tests to be performed.
April 2022.
Delivery of the first 6 vehicles of this project. This after a whole lot of delays caused by COVID and uncertainty over the homologation procedure and technical hurdles. The delivery, initially intended to start in 2019, has hence developed a significant delay.
December 2021.
New order received for 8 additional vehicles. Just in time as this generation of the used base vehicles will be stopped. We will just succeed to receive the base units from the last production runs.
July 2019.
the 10 vehicles out of the initial order are in production. An additional order for 2 off is received. Delivery of the vehicles will start this year.
December 2018.
After a lengthy tender-procedure of this Belgian government agency, the order has been granted to my customer. During 2018 several documents were requested to be replaced with more current versions. The order comprises 10 vehicles and all the maintenance and repair for the period of 7 years. The project is currently in the start-up phase.
November 2017.
After a couple of delays, the quotation for this tender has been presented.
July 2017.
After again a long period of silence, the specification for the quotation was received. All documents will be prepared to issue a correct quotation in this tender.
March 2017.
After a long period of silence, the request was received to submit the additional certificates that belong to the pre-selection phase.
September 2016.
Past August 2016 a pre-selection was launched for the delivery of a number of armored vehicles for a Belgian government agency. Support comprised the interpretation and translation of specifications and preparation of a lot of documents.