December 2018.
The second vehicle is delivered and put into operation. The project is completed.
June 2018.
After some issues with the first overhauled vehicle, now the second one is transported to the manufacturer for overhaul and modernization. This one has significantly more user-damage.
November 2017.
After a couple of setbacks and some misfortune, the vehicle picked up in June has been delivered back in October 2017. It is now under evaluation before the second will go into overhaul and modernization.
March 2017.
In the meantime, the specification for this modification and modernization for these armored trucks has been written and several quotations requested. The request of investment is issued.
September 2016.
A company that operates armored commercial vehicles asked to study whether the, close to 9 years old, vehicles still can be modified and renovated versus buying new ones. Given the basic vehicles it will be no problem to operate these vehicles until the age of 13 to 15 years. For that reason, a midlife-update, overhaul, security-upgrade and modification still is economically feasible. Coordinating and leading this process will be taken care of and will take a number of months to process.